Project Timeline (4-Month Duration)​

This timeline is considering only the BASE functionality required to meet the ideal specifications of this project.

If all addons were added, it would increase the timeline to approximately 6 months.

MonthTasksDuration
1stPlanning and MLS Integration
- Define project scope, objectives, and requirements2 weeks
- Connect website to MLS database for real-time updates2 weeks
Total: 4 weeks
2ndWebsite Development
- User Interface Design2 weeks
- Page Interaction & Home Interaction Data2 weeks
Total: 4 weeks
3rdData Collection & Automated Campaigns
- Backend Integration2 weeks
- Follow-Up Campaign1 weeks
- Suggested Properties Campaign1 weeks
Total: 4 weeks
4thTesting, Deployment, Monitoring & Support
- Testing2 weeks
- Deployment2 weeks
- Monitoring & SupportOngoing
Total: 4 weeks

Note: The timeline is designed to be concurrent, to meet a 4 month deadline.